Construction timetable

The cable from the turbine site to the grid is now in place, the turbine is being built, and we’re working to schedule for commissioning in early June. The main milestones are:

April: Foundation construction

May: Electrical balance of plant,  turbine delivery

31st May: grid connection completion by SSE

First week of June: Turbine construction and commissioning

We have also pencilled in the Saturday 12th July for our first AGM. This meeting will be on the site so will be a chance for all members to see the turbine in action!